JCP&L completes power reliability projects

Jersey Central Power & Light (JCP&L) has completed projects totaling more than $15 million throughout its northern and central New Jersey service areas that are expected to enhance customer service reliability.

The work included rebuilding transmission lines, upgrading substation equipment, and rebuilding infrastructure and reconnecting service to homes on the barrier islands that were damaged during Hurricane Sandy.

“With customers using more electricity during the summer months, we focus on completing major repairs and conducting ongoing maintenance prior to June 1,” said Anthony Hurley, vice president of operations for JCP&L. “Whether it be rebuilding transmission lines, upgrading substation equipment, or spending on vegetation management, our ultimate goal is to continue to enhance the reliability of our system to benefit our customers.”

The JCP&L projects include:

Energizing the rebuilt Whippany-Roseland 230 kV transmission line. This $12-million project included replacing 19 older style towers with new steel monopoles.

Reconnecting service to almost 30,000 customers in Monmouth and Ocean counties as repairs were completed on homes damaged by Hurricane Sandy. JCP&L will continue working with the remaining 1,900 customers who are continuing to make home repairs.

·      Rebuilding a 34.5 kV transmission line in Sussex County at a cost of $1 million.

·      Upgrading equipment at substations in Colts Neck and Neptune in Monmouth County.

·      Installing new poles to extend a distribution line and create a new connection point in Riverdale in Morris County.

·      Installing protective devices for the Oyster Creek Substation in Ocean County including capacitors to regulate system voltage.

·      Replacing utility poles and inspecting transformers and other equipment throughout the service area.

·      Installing animal guards, wire, fusing, and other equipment as part of circuit upgrades.

·      Installing equipment on additional circuits that can automatically restore customers to service following momentary outages, such as a tree branch falling on a line.

·      Replacing underground cable.

·      Completing vegetation management along 1,900 miles of circuits across the state.

JCP&L is a unit of FirstEnergy Corp. JCP&L serves 1.1 million New Jersey customers in the counties of Burlington, Essex, Hunterdon, Mercer, Middlesex, Monmouth, Morris, Ocean, Passaic, Somerset, Sussex, Union and Warren.

Previous articleBulwark Protective Apparel to assist storm recovery effort in Oklahoma
Next articleU.K. grants approval for 504 MW offshore wind farm
The Clarion Energy Content Team is made up of editors from various publications, including POWERGRID International, Power Engineering, Renewable Energy World, Hydro Review, Smart Energy International, and Power Engineering International. Contact the content lead for this publication at Jennifer.Runyon@ClarionEvents.com.

No posts to display