NV Dry Lake seeks approval for 200 MW Nevada solar power project

NV Dry Lake LLC told the Nevada Public Utilities Commission in a Sept. 4 notice of a recent application to the U.S. Bureau of Land Management for approval to construct a 200 MW (ac) solar photovoltaic facility.

The solar energy project would involve about one mile of 230-kV aboveground transmission line connecting to the existing Harry Allen Substation of Nevada Power, according to GenerationHub.

The project is to be located within the Dry Lake Solar Energy Zone about 15 miles northeast of Las Vegas in Clark County, Nevada.

The notice said the NV Dry Lake project would be constructed between September 2015 and December 2016, with commercial operation in December 2016.

Previous articleBrazil to spend $97 billion on power generation in new energy policy
Next articleTVA hopes to load fuel at Watts Bar 2 nuclear power plant in March 2015
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior to that as editor of SNL Energy's Coal Report. He was formerly with Coal Outlook for 15 years as the publication's editor and contributing writer, and prior to that he was editor of Coal & Synfuels Technology and associate editor of The Energy Report. He has a bachelor's degree from Central Michigan University.