Georgia Power marks milestones in Plant Vogtle nuclear plant expansion

Georgia Power continues to track positive progress in the construction of the new Vogtle units 3 and 4 facility near Waynesboro, Georgia. The project, among the first new nuclear units to be built in the U.S. in three decades, has marked several milestones in 2013.

Following the placement of 7,000 cubic yards of concrete for the Unit 3 basemat in March, additional project progress this year has included:

·      Delivery of the Unit 3 reactor vessel and the Unit 4 deaerator to the site.

·      Placement of the CR10 “cradle” module in the Unit 3 nuclear island.

·      Placement of the containment vessel bottom head (CVBH).

·      Installation of rebar in the Unit 3 auxiliary building walls.

·      Placement of the Unit 4 nuclear island mudmat and installation of the Unit 4 basemat rebar.

Construction of key modules continues to progress, as does work on the cooling towers for both units, condenser pre-assembly, permanent office building construction, switchyard work and raw water intake structure preparation. In addition, activities to ensure readiness for the transition to commercial operation are underway including employing and training operational personnel, developing pre-operational and startup testing, and developing operations programs and procedures. In fact, there are currently nearly 100 licensed operator candidates in different phases of the training program with 25 of these candidates being certified on the AP1000 on-site limited scope simulator in February.

Georgia Power is the largest unit of Southern Co.