PGE, BPA talk transmission projects

@font-face {“Cambria”; }p.MsoNormal, li.MsoNormal, div.MsoNormal { margin: 0in 0in 0.0001pt; font-size: 12pt;”Times New Roman”; }a:link, span.MsoHyperlink { color: blue; text-decoration: underline; }a:visited, span.MsoHyperlinkFollowed { color: purple; text-decoration: underline; }div.Section1 { page: Section1; }

Portland, Ore., February 17, 2011 — Portland General Electric entered into a memorandum of understanding with the Bonneville Power Administration that allows the two utilities to coordinate planning of new electrical substations and transmission facilities and to consider joint development.

PGE has proposed Cascade Crossing, a double-circuit transmission project running from the city of Boardman to the Salem area, to help meet Oregon’s growing energy needs, enhance reliability of the electrical grid, and allow for development of more renewable power projects to help meet the state’s renewable energy standard.

The project would connect new and existing energy generating resources east of the Cascades to the Willamette Valley.

BPA is building the McNary-John Day transmission project, which will be completed in January 2012. BPA is conducting environmental analysis on three proposed 500-kV transmission lines. In addition, BPA is developing several large electrical substations to integrate wind generation into the Northwest grid.

The MOU allows PGE and BPA to share confidential information as they work together on a range of issues, including system interconnections, substation locations and use of existing transmission corridors.

PGE previously executed MOUs for discussions surrounding Cascade Crossing with PacifiCorp, Idaho Power and the Confederated Tribes of Warm Springs. To build the project, PGE must obtain approvals from both the state and federal governments. PGE is in the second year of what is expected to be a three-year permitting process, which includes a variety of opportunities for public input.

Previous articleJ.D. Power ranks top utilities for outage restoration
Next articleProgress Energy CEO: Nuclear energy has a challenging, promising future
The Clarion Energy Content Team is made up of editors from various publications, including POWERGRID International, Power Engineering, Renewable Energy World, Hydro Review, Smart Energy International, and Power Engineering International. Contact the content lead for this publication at Jennifer.Runyon@ClarionEvents.com.

No posts to display