Wind can’t be large grid’s main source of electricity

Wind energy, because of its variable nature, is not suited to be the lone or primary source of a grid’s total electricity, according to a new Reason Foundation study. If it is used to produce more than 10 to 20 percent of a system’s electricity, wind power increases operating costs because of the need for expensive storage facilities or continuously available carbon dioxide-emitting backup power generation facilities.

The report uses a full year’s worth of hourly power grid data from PJM Interconnection, which manages the electrical grid in part of the eastern United States, to simulate how wind would’ve supplied the necessary power to customers in 2009. Reason’s models show wind power would’ve failed to supply all of the electricity PJM customers needed more than 50 percent of the time.

If wind is going to produce a large percentage of a grid’s electricity, it will be necessary to build expensive energy storage facilities or reserve power generation facilities to supply power when there is not enough wind to meet energy demands at any given time and to prevent brownouts and blackouts.

The study shows that as more reserve power is needed, the environmental benefits of wind power decrease because of the CO2 emissions from those facilities, which rely on fossil fuels and must operate even when not being used, to ensure electric grid reliability.

The study concludes that given the costs involved, the practical upper limit for wind power’s contribution to an electricity grid is 10 percent of the total energy, which would produce a 9 percent reduction in CO2 emissions.

“Very high wind penetrations are not achievable,” said William Korchinski, author of the study. “As wind’s share increases, system reliability will be adversely affected disproportionately unless adequate reserve power is available. That power reserve is expensive and lowers any possible environmental benefits.”


Click here for report

Previous articleEl Paso Electric buys 50 MW of solar energy from new power plant
Next articleLIPA COO resigns after Sandy outage response criticized