UI to invest in Connecticut Light and Power transmission projects

Berlin, Conn., July 15, 2010 – The United Illuminating Co. and The Connecticut Light and Power Co. filed a joint application with the Connecticut Department of Public Utility Control seeking approval for UI’s investment in and ownership of transmission assets associated with the Connecticut portion of CL&P’s New England East West Solution projects to improve regional energy reliability.

NEEWS consists of four interrelated transmission projects being developed by subsidiaries of Northeast Utilities, the parent company of CL&P, in collaboration with National Grid USA.

Three of the projects have portions sited in Connecticut: (1) the Greater Springfield Reliability Project, (2) the Interstate Reliability Project and (3) the Central Connecticut Reliability Project.

Based on data prepared by CL&P, UI expects the cost of building the Connecticut portion of these projects will be about $711 million.

Under the terms of an agreement between UI and CL&P, which will be subject to state and federal regulatory approval, UI has the option to make quarterly payments to CL&P in exchange for ownership of specific transmission assets as they come into commercial operation.

Following regulatory approval, UI will have the right to invest up to the greater of $60 million or an amount equal to 8.4 percent of CL&P’s costs for the Connecticut portions of these projects.

As assets come into commercial operation, CL&P will transfer title to transmission assets such as poles and wires to UI in proportion to its investments, but CL&P will continue to maintain these portions of the transmission system once they are in operation pursuant to an operating and maintenance agreement with UI.

UI’s investments are expected to be made over a period of three years based on current project completion projections.

This proposed transaction follows the successful collaboration of CL&P and UI on the 345-kV Middletown-to-Norwalk Transmission Project, where each party owns portions of the line. The Middletown-to-Norwalk Transmission Project went into commercial operation at the end of 2008.

 